Active engagement
At RiskOversightUES Prewar Combo — Phase 1–2
412 E 74th St, Unit 12A/B · Manhattan. Owner-side oversight on a gut renovation combining two prewar units. Primary pressure points are kitchen allowances, DOB self-cert revisions, and a pending MEP change order package.
- GC
- Northline Builders
- Architect
- Hale + Mercer
- Construction value
- $3.20M
- Target close
- Nov 18, 2026
Budget
$2.48M
of $3.20M committed
RFIs
12
4 still open
Change orders
$72K
Pending review
Schedule
−9 days
vs baseline
Risk board
6 shown · 3 open · 1 active issues
| Risk | Trade | Severity | Status | Exposure |
|---|---|---|---|---|
| Kitchen / Appliances | Issue | Open | $18–28K | |
| MEP | At Risk | Open | $41,860 | |
| Millwork | At Risk | Open | Time risk / possible accel. premium | |
| Plumbing / DOB | At Risk | Watching | Schedule only (est. 5–8 days) | |
| Building / GC | On Track | Watching | — | |
| Tile / Waterproofing | On Track | Resolved | — |